web analytics
2.52 MWp Ground-Mounted Solar PV Project with Single-axis Trackers in Abruzzo Central Italy

Sabu Bozhayeva

Property Types

  • 9% Renewable Energy - Solar PV
  • 8% Renewable Energy
  • 7% Data Centers
  • 77% Other

Property Status

  • 98% For Sale
  • 2% For Rent

Property Cities

  • 18% Chamonix
  • 16% Madrid
  • 16% Sofia
  • 51% Other

About Sabu Bozhayeva

0 Review

Sort by:
Leave a Review

Leave a Review

The Project comprises a 2.52 MWp plant with bifacial modules on single-axis trackers and a 2.50 MW grid injection capacity, with an accepted medium-voltage grid connection solution from the local distribution system operator (DSO) and the land secured through preliminary surface-rights agreements.

Construction is currently scheduled to start in Q1 2027. The opportunity is suited to IPPs, infrastructure and energy-transition funds, and industrial investors seeking a mid-size, near-construction position in the Italian solar market.

INVESTMENT HIGHLIGHTS

KEY PROJECT DATA

Location Abruzzo region, Central Italy
Technology Ground-mounted PV, bifacial monocrystalline modules (715 Wp class) on single-axis trackers
Installed capacity (DC) 2,522.52 kWp (3,528 modules; 126 strings of 28 modules)
Grid injection capacity (AC) 2,500 kW
Inverters / transformer 8 × 320 kW (2,560 kW total) / 1 × 1,600 kVA
Expected production 3,683 MWh/year (1,460 equivalent hours)
Site area 48,090 m² cadastral area; 10,566 m² plant area (c. 22%)
Land rights Preliminary surface-rights agreements with the landowners for c. €29k per year in aggregate
Permitting route Single Regional Authorisation (Autorizzazione Unica) including zoning change to industrial use
Grid connection New customer delivery substation (DSO standard box) connected in-out on an existing 20 kV MV line; c. 1.8 km underground Al 185 mm² cable; 103 working days for DSO works
Expected start of construction 1 March 2027

DEVELOPMENT STATUS & MILESTONES

June 2023 Grid connection request submitted to the DSO
September 2023 First connection quote received
February 2024 Amendment requested for an underground cable solution
May 2024 Amended connection quote received and accepted (connection fee €246k excl. VAT; 30% paid)
November 2024 Detailed design of the grid connection works (PTO) submitted
Q1 2027 Expected start of construction

Note: status of the Single Regional Authorisation and validity of the grid solution to be confirmed in the data room.

INDICATIVE ECONOMICS (SELLER ESTIMATES)

Total CAPEX €2,283,421 (c. €0.91/Wp)
Expected annual revenue €313,045 (implied c. €85/MWh)
Annual operating costs €65,314
Expected annual EBITDA c. €247,700 (c. 79% margin)
Grid connection cost €246,211 excl. VAT (€73,863 paid; c. €37,789 refundable by the DSO after testing if the grid works are self-built)
Illustrative unlevered pre-tax IRR c. 9–10%

Illustrative IRR computed by MergersCorp on Seller figures: 25–30-year life, flat revenue and operating costs, 0.4% annual module degradation, no leverage, no tax and no terminal value. For indicative purposes only.

PROPOSED TRANSACTION & PROCESS

MergersCorp M&A
International As Seen On

  • brand 1
  • brand 1
  • brand 1
  • brand 1
  • brand 1