web analytics
10.2 MW Agrivoltaic Solar Project with Tracker Technology

Sabu Bozhayeva

Property Types

  • 7% Renewable Energy - Solar PV
  • 6% Banks
  • 6% Financial Services
  • 81% Other

Property Status

  • 98% For Sale
  • 2% For Rent

Property Cities

  • 18% Chamonix
  • 16% Madrid
  • 16% Sofia
  • 51% Other

About Sabu Bozhayeva

0 Review

Sort by:
Leave a Review

Leave a Review

The Project has a grid injection capacity of 10.2 MW and a current design of c. 12.7 MWp, using bifacial modules on single-axis trackers combined with continued agricultural use of the land.

The Project is being authorised through the Simplified Authorisation Procedure (PAS) at municipal level: the application was filed with the municipal One-Stop Shop (SUAP) in July 2026 and the supplementary town-planning documentation requested by the municipality was submitted in September 2026. The grid connection solution issued by Terna provides for a 150 kV antenna connection to a new switching substation of the national transmission grid. The opportunity suits IPPs, infrastructure and energy-transition funds and industrial investors seeking a mid-size, advanced-stage Italian solar asset.

INVESTMENT HIGHLIGHTS

KEY PROJECT DATA

Location Lazio region, Central Italy (province north of Rome); agricultural area at c. 160 m above sea level, reached via a farm road off a state road
Technology Agrivoltaic, ground-mounted; single-axis E-W trackers (N-S axis); bifacial monocrystalline N-type modules (650 Wp)
Capacity 10.2 MW grid injection; 12.727 MWp DC (rated capacity 10.67 MW per the parcel plan)
Main equipment (current design) 19,580 modules; 3 SMA Sunny Central UP central inverters (2 × 3,060 kVA + 1 × 4,200 kVA) in MV power stations; 30 kV MV network; 30/150 kV user substation
Site Single cadastral parcel of c. 17.3 ha project area (c. 14.3 ha occupied by the plant, including mitigation areas, roads and fencing); currently cereals and forage, to be replaced by crops defined in an agronomic plan
Grid connection Terna STMG: 150 kV underground cable in antenna to a new 150 kV RTN switching substation, inserted in-out on an existing 150 kV line
Land rights Plant parcel: preliminary purchase agreement with the sole owner. Cable route: easements over c. 5 private parcels (c. 1.2 km, c. 2,500 m² of easement strip; estimated compensation c. €2k) plus farm roads
Permitting route Simplified Authorisation Procedure (PAS) – municipal SUAP/SUE
Incentives Route to market through merchant sales and/or PPA (eligibility for support schemes to be assessed by the buyer)

DEVELOPMENT STATUS & MILESTONES

March 2026 Electrical design and electromagnetic-field report completed
July 2026 PAS application filed with the municipal One-Stop Shop (SUAP); parcel plan issued
August 2026 SUAP receipt issued (30-day term for silent consent)
September 2026 Municipality requests re-filing of the town-planning documents on its building portal (SUE) within 60 days; supplementary documentation submitted on 11 September 2026

Note: the outcome of the PAS procedure and the status of the grid connection solution (acceptance and validity) will be confirmed in the data room.

INDICATIVE ECONOMICS

Illustrative specific yield c. 1,750–1,850 kWh/kWp (single-axis trackers with bifacial modules in Central Italy)
Illustrative annual production c. 22–23.5 GWh (year 1)
Illustrative annual revenue c. €1.7–2.0m at an assumed captured price of €75–85/MWh
CAPEX / energy yield report Not included in the documentation received; to be provided in the data room

No energy yield report or cost estimate was provided with the project documents. The figures above are MergersCorp benchmark assumptions for indicative purposes only and are not forecasts.

PROPOSED TRANSACTION & PROCESS

MergersCorp M&A
International As Seen On

  • brand 1
  • brand 1
  • brand 1
  • brand 1
  • brand 1