A 12.73 MWp agrivoltaic solar photovoltaic project located in the Lazio region of central Italy. The project covers approximately 20.32 hectares and is designed to combine renewable electricity generation with continued agricultural land use. Its technical configuration achieves a Land Occupation Ratio (LAOR) of 38.27%, remaining below the applicable 40% threshold. The project has reached a significant permitting milestone, with the simplified authorization procedure (PAS) completed through the administrative silence-assent mechanism, according to the documentation provided.
KEY PROJECT HIGHLIGHTS
- Installed Capacity: 12.73 MWp
- Total Land Area: Approximately 20.32 hectares
- Area Occupied by PV Modules: Approximately 14.30 hectares
- Land Occupation Ratio (LAOR): 38.27%
- Specific Energy Yield: 1.40 GWh/ha/year
- Grid Connection Allocation: Approximately €14,130 (excluding VAT)
- Technology: Agrivoltaic solar PV
TECHNICAL OVERVIEW
The project features an agrivoltaic configuration designed to optimize land utilization while maintaining agricultural compatibility.
Key technical parameters include:
- LAOR of 38.27%, below the 40% threshold indicated in the project documentation.
- Specific energy yield of 1.40 GWh/ha/year, compared with the 1.07 GWh/ha/year agrivoltaic reference benchmark provided.
- Compliance with the specified minimum agrivoltaic-to-standard photovoltaic productivity ratio of 0.60.
GRID CONNECTION
The project benefits from an allocated grid-connection cost based on the applicable Terna transmission network estimate.
- Total Standard Terna Grid Works Estimate: €450,000
- Project Allocation Coefficient: 3.14%
- Allocated Grid Connection Contribution: Approximately €14,130, excluding VAT
- Connection Configuration: Connection via a new 150 kV electrical substation and associated connection infrastructure.
The proposed grid infrastructure includes a new 150 kV electrical substation and connection works associated with the existing transmission network.
PERMITTING & DEVELOPMENT STATUS
The project has progressed through the principal milestone of its simplified authorization procedure (PAS).
| Milestone |
Status / Timeline |
| PAS application submitted |
11 September 2026 |
| Authorization perfected through silence-assent procedure |
21 October 2026 |
| Publication in the Official Bulletin of the Lazio Region |
Scheduled for 5 November 2026 |
| Deadline to commence construction |
Within 18 months, subject to applicable TICA provisions and relevant contractual conditions |
| New 150 kV electrical substation |
Estimated construction period: 16 months |
| Grid connection works |
Estimated 8 months + 1 month per km |
INVESTMENT RATIONALE
- Advanced permitting: The PAS procedure has reportedly reached completion through the silence-assent mechanism.
- Attractive project scale: 12.73 MWp of planned installed capacity.
- Agrivoltaic land-use efficiency: LAOR of 38.27%, within the stated regulatory threshold.
- Strong technical productivity: Project-specific energy yield of 1.40 GWh/ha/year.
- Grid infrastructure planning: Defined connection configuration and allocated grid-connection contribution.
- Strategic location: Situated in the Lazio region, Italy, within the country’s established renewable energy market.