web analytics

Properties

357 Properties
Sort by:
The project has achieved Ready-to-Build (RTB) status, de-risking the development phase and securing all primary structural entitlements. The asset is currently non-operational and remains in pre-construction posture pending financial close and issuance of the Notice to Proceed (NTP).

Entitlement & Milestone Overview

Milestone Domain Development Status Operational Status
Land Control 100% secured via long-term lease / purchase options Non-operational
Zoning & Permitting Fully approved; discretionary approvals received Pre-construction
Interconnection / Grid Access Interconnection agreement executed; study phase closed De-energized / inactive
Offtake / Commercial Structure PPA / revenue framework established or shortlisted No commercial generation/revenue
Engineering (Basic) Preliminary FEED / 30–60% detailed design complete Construction not commenced

Transition Plan: RTB to Commercial Operation Date (COD)

Bringing the asset to full operational capability requires execution across three remaining phases:
  1. Procurement & Contracting:
    • Finalize the balance-of-plant (BOP) and Engineering, Procurement, and Construction (EPC) contract.
    • Lock in long-lead equipment supply agreements and warranties.
  2. Financing & Notice to Proceed (NTP):
    • Finalize tax equity / project debt syndication.
    • Reach Final Investment Decision (FID) and issue Full NTP to the general contractor.
  3. Construction, Commissioning & Energization:
    • Break ground and execute physical build-out under the designated construction schedule.
    • Conduct testing, interconnection tie-in, grid compliance trials, and final commissioning to achieve COD.

High-Level Delivery Timetable

Milestone Target Horizon Core Objective
FID & Full NTP Month 0 Release funds and commence site mobilization
Substantial Completion Months 10–14 Mechanical and electrical completion
Grid Energization & Testing Months 14–16 Hot commissioning, sync trials, and punch list resolution
Commercial Operation Date (COD) Month 16 Transition to revenue-generating operational management

Key Risks & Value Drivers

  • Value Realized: By advancing the asset to RTB, the project eliminates primary regulatory, land-use, and permitting risks, creating an immediate, financeable infrastructure asset.
  • Near-Term Focus: Mitigating supply-chain lead times, firming up EPC cost certainty, and closing financing to protect the target COD and projected rate of return.

MergersCorp M&A
International As Seen On

  • brand 1
  • brand 1
  • brand 1
  • brand 1
  • brand 1