The Project comprises a 2.52 MWp plant with bifacial modules on single-axis trackers and a 2.50 MW grid injection capacity, with an accepted medium-voltage grid connection solution from the local distribution system operator (DSO) and the land secured through preliminary surface-rights agreements.
Construction is currently scheduled to start in Q1 2027. The opportunity is suited to IPPs, infrastructure and energy-transition funds, and industrial investors seeking a mid-size, near-construction position in the Italian solar market.
INVESTMENT HIGHLIGHTS
Secured grid access
20 kV MV connection solution issued by the DSO, amended to an underground-cable route and accepted in May 2024; 30% of the connection fee already paid and the detailed design of the grid works (PTO) submitted in November 2024.
Efficient technology
3,528 bifacial monocrystalline 715 Wp modules on single-axis trackers, 8 × 320 kW string inverters and a 1,600 kVA transformer, delivering a specific yield of c. 1,460 kWh/kWp.
Compact, low-impact footprint
the plant occupies c. 1.06 ha of a c. 4.8 ha site (c. 22% coverage) on land zoned as building land, reducing land-use and landscape sensitivities.
Competitive cost base
total CAPEX of c. €2.28m (c. €0.91/Wp), with annual operating costs of c. €65k.
Attractive cash generation
expected revenues of c. €313k p.a. and EBITDA of c. €248k p.a. (c. 79% margin) based on Seller estimates.
Supportive market
Italy’s National Energy and Climate Plan (PNIEC) targets c. 80 GW of installed solar PV by 2030, underpinning demand for construction-ready capacity.
2,522.52 kWp (3,528 modules; 126 strings of 28 modules)
Grid injection capacity (AC)
2,500 kW
Inverters / transformer
8 × 320 kW (2,560 kW total) / 1 × 1,600 kVA
Expected production
3,683 MWh/year (1,460 equivalent hours)
Site area
48,090 m² cadastral area; 10,566 m² plant area (c. 22%)
Land rights
Preliminary surface-rights agreements with the landowners for c. €29k per year in aggregate
Permitting route
Single Regional Authorisation (Autorizzazione Unica) including zoning change to industrial use
Grid connection
New customer delivery substation (DSO standard box) connected in-out on an existing 20 kV MV line; c. 1.8 km underground Al 185 mm² cable; 103 working days for DSO works
Expected start of construction
1 March 2027
DEVELOPMENT STATUS & MILESTONES
June 2023
Grid connection request submitted to the DSO
September 2023
First connection quote received
February 2024
Amendment requested for an underground cable solution
May 2024
Amended connection quote received and accepted (connection fee €246k excl. VAT; 30% paid)
November 2024
Detailed design of the grid connection works (PTO) submitted
Q1 2027
Expected start of construction
Note: status of the Single Regional Authorisation and validity of the grid solution to be confirmed in the data room. INDICATIVE ECONOMICS (SELLER ESTIMATES)
Total CAPEX
€2,283,421 (c. €0.91/Wp)
Expected annual revenue
€313,045 (implied c. €85/MWh)
Annual operating costs
€65,314
Expected annual EBITDA
c. €247,700 (c. 79% margin)
Grid connection cost
€246,211 excl. VAT (€73,863 paid; c. €37,789 refundable by the DSO after testing if the grid works are self-built)
Illustrative unlevered pre-tax IRR
c. 9–10%
Illustrative IRR computed by MergersCorp on Seller figures: 25–30-year life, flat revenue and operating costs, 0.4% annual module degradation, no leverage, no tax and no terminal value. For indicative purposes only. PROPOSED TRANSACTION & PROCESS
Perimeter
acquisition of 100% of the project company holding the Project’s rights, permits, grid connection and land agreements.
Structure
share deal (to be confirmed); consideration and payment terms to be proposed by bidders.
Next steps
execution of a Non-Disclosure Agreement, followed by access to an Information Memorandum and virtual data room, and submission of non-binding indications of interest.